
Ryan & Greene Team
Construction Experts
Three years ago, an in-law suite was an occasional request. In 2026, it is one of the most common addition conversations we have with Southern New Hampshire homeowners. Aging parents are leaving high-cost assisted living, adult children are moving home to save for a down payment, and remote work has made a private second living space genuinely useful. New Hampshire law has caught up too — recent legislation has made it dramatically easier to add an accessory dwelling unit (ADU) in Merrimack, Bedford, Nashua, Manchester, and the surrounding Merrimack Valley towns. This guide walks through what the new rules actually allow, what these projects cost in 2026, and the design and septic decisions that quietly make or break the build.
Key Takeaways
- •NH ADUs are now by-right statewide under RSA 674:71-73, and HB 577 (2025) forces every town to allow either an attached or detached unit.
- •2026 Southern NH cost ranges: attached in-law suite $225K–$350K+, basement conversion $110K–$185K, detached ADU $250K–$450K, bedroom/bath-only suite $95K–$165K.
- •Plan on 9–12 months start to finish; septic capacity review (NHDES) is the most common hidden cost at $20K–$40K if an upgrade is required.
- •Design priorities that matter most: separate entrance, universal design, ductless mini-split HVAC, Rockwool soundproofing, and an electrical sub-panel.
In-Law Suite vs. ADU: What's the Difference?
The terms get used interchangeably, but they are not the same thing in the eyes of NH building code. An "in-law suite" is a bedroom suite — typically a bedroom, full bath, and sitting area — that shares the main home's kitchen and entrance. An "ADU" (accessory dwelling unit) is a fully independent living space with its own kitchen, bath, sleeping area, and separate entrance. The ADU classification triggers different permitting, septic calculations, and resale value, so the kitchen question (full stove or just a kitchenette) is one of the first design decisions we work through with clients.
- •Attached ADU — a bump-out addition, second-story addition, or basement conversion that shares a wall with the main house
- •Detached ADU — a stand-alone cottage, often 600–1,000 sq ft, on the same lot
- •Garage conversion ADU — converting an existing attached or detached garage into living space
- •In-law suite (non-ADU) — bedroom, bath, and sitting room without a full kitchen; simpler permitting, no separate utilities required

NH ADU Law in 2026: What Recently Changed
New Hampshire's ADU statute lives in RSA 674:71-73. The biggest update homeowners need to know about is HB 577, signed in July 2025 and in effect throughout 2026. Combined with earlier reforms, here is where the rules stand right now in Southern NH:
- •Every municipality that allows single-family homes must allow at least one ADU by right — towns can no longer ban them outright
- •HB 577 (2025) requires towns to allow either an attached OR a detached ADU on single-family lots — towns can no longer prohibit detached units across the board
- •State law prevents towns from capping ADU size below 750 sq ft; many Southern NH towns allow up to 1,000 sq ft for attached units
- •Towns can still require the owner to live in either the main home or the ADU (most do)
- •Municipalities cannot require more than two additional off-street parking spaces
- •Towns cannot restrict ADU occupants to family members — long-term rental is legal
In plain English: if you own a single-family home in Southern NH and you live in either the main house or the ADU, your town almost certainly has to let you build one. The conversation has shifted from "is this allowed?" to "what are the local design and septic requirements?"
Town-by-Town Notes for Southern NH
State law sets the floor, but Southern NH towns each layer on their own design standards, impact fees, and septic reviews. Here is what we are seeing in the towns we work in most often:
- •Merrimack — Detached ADUs by right. Up to 1,000 sq ft attached. Strict on aesthetic continuity with the main house (matching siding, trim, roof pitch).
- •Bedford — Detached by right, up to 1,000 sq ft. Known for high architectural standards; minor setback issues often need a quick ZBA visit.
- •Nashua — Most flexible Southern NH city. ADUs allowed in many multi-family zones in addition to single-family lots. Up to 1,000 sq ft.
- •Manchester — By-right detached "carriage house" style units in many neighborhoods. Attached units typically capped at 750 sq ft in older single-family zones.
- •Amherst & Hollis — Allowed, but septic review by NHDES is the long pole in the tent due to high water tables and rural lot conditions. Cottage-style detached units encouraged.
- •Windham — Allowed up to 1,000 sq ft. Charges an impact fee for the added dwelling — typically a few thousand dollars.
- •Londonderry, Derry, Salem, Hudson — All compliant with state law as of 2026. Specifics on parking and setbacks vary; we verify each project against the current local ordinance before drawing plans.
2026 Cost Ranges in Southern NH
Pricing in 2026 has stabilized after two volatile years, but Southern NH labor and trade costs remain among the highest in the state. These ranges reflect what we are quoting and what other reputable contractors in Merrimack, Bedford, and Nashua are landing on for fully permitted, code-compliant work. They assume reasonable site access and existing utility service that can be extended.
- •Attached in-law suite or ADU bump-out (500–800 sq ft): $225,000–$350,000+, roughly $275–$400 per sq ft. Drivers: new foundation, roof tie-in, HVAC integration.
- •Basement conversion to ADU (600–900 sq ft): $110,000–$185,000, roughly $150–$225 per sq ft. Drivers: egress windows, moisture mitigation, ceiling height work, plumbing rough-in.
- •Garage conversion to ADU (400–600 sq ft): $130,000–$210,000. Drivers: floor reinforcement (most garage slabs slope to the door), full insulation, plumbing through concrete, new exterior wall where the overhead door was.
- •Detached ADU / cottage (600–1,000 sq ft, new build): $250,000–$450,000, roughly $350–$500 per sq ft. Drivers: independent utility trenching, separate foundation, complete site prep.
- •Bedroom-and-bath in-law suite (no full kitchen, 300–500 sq ft): $95,000–$165,000. Simpler scope, no separate utilities, faster permitting.
The single largest hidden cost in Southern NH is septic. Adding an ADU is legally treated as adding a bedroom, which means NHDES re-evaluates your existing septic system's capacity. If your current system is rated for three bedrooms and you are now operating a four-bedroom-equivalent property, you have to upgrade. A full septic replacement in Southern NH runs $20,000–$40,000 depending on soil conditions and whether you need an engineered system. We always order a septic capacity review before pricing the build so this never shows up as a surprise.
Design Decisions That Actually Matter
After dozens of in-law suite and ADU projects, the design details that consistently make the difference are not the finishes — they are the layout, the soundproofing, and the systems decisions. A few that we push every client to think about hard:
- •Separate entrance — non-negotiable for ADUs by law, but even non-ADU in-law suites benefit hugely from a private side door. It protects everyone's sanity.
- •Universal design — zero-step entry, 36-inch interior doors, curbless walk-in shower with grab-bar blocking pre-installed in the walls. If the suite is for aging parents, you want this on day one, not as a retrofit five years later.
- •Ductless mini-split HVAC — the 2026 standard for ADUs and in-law suites in NH. Independent climate control, no ductwork through existing walls, and far easier to add to a conversion.
- •Soundproofing — Rockwool insulation in shared walls and ceilings plus resilient channels on the ceiling drywall. The single most common complaint in poorly-built attached suites is hearing footsteps and conversation from the other unit.
- •Electrical sub-panel — give the ADU its own sub-panel off the main service. Avoids tripped breakers when both units run dryers or AC at once, and makes it possible to add separate metering later if you ever want to.
- •Kitchenette vs. full kitchen — full stove plus a 30" range hood vents the suite as ADU under NH code. If you go with just a microwave and induction cooktop, it stays an in-law suite and skips some permitting complexity, but you lose the rental-income option.
Permitting and Realistic Timeline
Homeowners almost always underestimate this part. A well-run in-law suite or ADU project in Southern NH runs 9–12 months from first call to move-in. The construction is the shortest piece. Here is the realistic breakdown we share at the first meeting:
- •Months 1–2: Feasibility, site survey, septic verification, architectural drawings, and contractor selection
- •Months 3–4: NHDES septic approval (4–6 weeks if needed), town building permit (2–4 weeks in most Southern NH towns), zoning board only if a variance is required (adds ~2 months)
- •Months 5–11: Construction — typically 6–8 months for an attached suite or conversion, longer for a detached ADU with new utility runs
- •Final 2–4 weeks: Final inspections, certificate of occupancy, punch list
If you want a parent moved in by next summer, the time to call a contractor is right now. Waiting until fall to start design almost always means the project does not finish until the following fall.
The Financial Case for an ADU in 2026
The numbers on these projects have gotten genuinely compelling in Southern NH. A few benchmarks worth running through with your accountant or financial planner:
- •Long-term rental income: a one-bedroom ADU in the Merrimack–Nashua corridor is renting for $2,100–$2,450 per month in 2026 (NHHFA fair market rent data plus current Rentometer comparables)
- •Assisted living comparison: average assisted living in NH runs $7,500–$9,000 per month — an in-law suite that lets a parent stay home pays for itself in avoided costs in roughly 3–4 years
- •Resale value: Southern NH appraisers are giving ADU additions a 1:1 dollar-for-dollar return, and "multigenerational capable" is now a primary search filter for buyers in this market
- •Financing: most clients use a HELOC or cash-out refinance; the FHA 203k renovation loan is still useful for buyers who want to purchase a home and build the ADU in one financed package
5 Mistakes We See Homeowners Make
- •Skipping the septic review. Assuming "it's just a small suite" will not trigger NHDES. It will, and finding out at permit time can stall the project by months.
- •Cheaping out on soundproofing. Standard fiberglass batt in a shared wall is not enough — you will hear everything. Spend the extra $1,500–$3,000 on Rockwool and resilient channels.
- •Making the addition look like an obvious addition. Roof pitch, siding profile, trim details, and window proportions need to match the original home. Mismatched additions hurt resale and curb appeal.
- •No electrical sub-panel. A single shared 200-amp panel running two full households trips constantly. Plan for a sub-panel from day one.
- •Hiring on price alone. The lowest bid on an ADU project is almost always missing line items — septic, permit fees, sub-panel, finished landscaping — that the homeowner ends up paying for later. Get itemized scopes from two or three reputable contractors and compare them line by line.
Frequently Asked Questions
Do I need a separate septic system for an ADU in Southern NH?
Usually no — but your existing system has to have enough rated capacity for the added bedroom equivalent. NHDES treats an ADU as adding a bedroom to the property. If your current system is at capacity, you will need to upgrade it before the town will issue an ADU certificate of occupancy. Budget $20,000–$40,000 for a full septic replacement if it is required. We order a capacity review before quoting any ADU project so there are no surprises.
Can my town still ban ADUs in 2026?
No. Under RSA 674:72, every NH town that allows single-family homes must allow at least one ADU per single-family lot. As of HB 577 (July 2025), towns also cannot ban detached ADUs outright — they must allow either attached or detached. Towns can still set reasonable design standards, owner-occupancy rules, and setback requirements, but a blanket ban is no longer legal.
Can I rent the ADU on Airbnb or as a long-term rental?
Long-term rental (30+ days) is allowed by state law — towns cannot restrict ADU occupants to family members. Short-term rental (Airbnb, VRBO) is a separate question and depends on your specific town's short-term rental ordinance. Several Southern NH towns now require a short-term rental permit or restrict them entirely in residential zones, so verify locally before banking on Airbnb income.
What is the difference in cost between converting a basement and building an attached bump-out?
A basement conversion to a code-compliant ADU typically runs $110,000–$185,000 because you are working with an existing shell — you mainly need egress windows, moisture mitigation, plumbing, HVAC, and finishes. An attached bump-out addition runs $225,000–$350,000+ because you are pouring a new foundation, framing new walls and roof, and tying into the existing structure. Basements are usually the faster and cheaper path if you have the ceiling height and a good way to add a private entrance.
How long does an in-law suite project actually take?
Plan on 9–12 months from your first contractor meeting to move-in. Design and engineering take 1–2 months, septic and permit approvals take another 1–2 months, and construction itself runs 6–8 months for most attached suites and conversions. Detached ADUs with new utility runs trend toward the longer end of that range. If you need a parent moved in by next summer, start the conversation now.
Ryan & Greene Construction designs and builds in-law suites and ADU additions throughout Merrimack, Bedford, Nashua, Manchester, Hudson, Londonderry, Derry, Windham, and the rest of the Merrimack Valley. We handle the septic review, the town permits, and the architectural drawings as part of the project — you get one team from first sketch to move-in. Browse our home additions service page for project examples, model your build with our free addition cost estimator, or request a free consultation and we will walk through what is realistic for your lot, your budget, and your timeline.
Ready to Start Your Project?
Get a free, no-obligation estimate for your renovation project.

